Modernisation of the tram route in the section of Aleje Jerozolimskie from the Banacha terminal loop to the Gocławek terminal loop

Investor: Tramwaje Warszawskie Sp. z o.o.

Project description: Modernisation of tracks and platforms (with the use of up-to-date technologies in the form of vibration-absorbing mats reducing the noise level and shortening travel times), repair of the catenary network and modernisation of catenary substations, as well as the power wiring system the route includes the following street sections: Grójecka, Aleje Jerozolimskie, 3-go Maja, ks. Józefa Poniatowskiego, Jerzego Waszyngtona and Grochowska – from the Banacha to Gocławek terminal loop

Period of delivery: 27th April 2007 - 15th November 2007 

Project gross value: PLN 81 675 678.31
 